Sikkim moves closer to first rail link as Indian Railways completes excavation of all 14 tunnels
Babushahi Bureau/PIB
New Delhi, November 28, 2026: Sikkim has moved a step closer to joining India’s railway network, with Indian Railways completing excavation work on all 14 tunnels of the 45-km Sivok-Rangpo new railway line project.
The breakthrough was achieved on November 27 in Tunnel No. 10, the longest tunnel on the route, measuring 5.3 km. The completion of excavation marks a major construction milestone for the strategically important Himalayan railway project.
Tunnel No. 10 was excavated from both ends and through two access tunnels. With the excavation fronts now connected, work will move to the remaining stages, including tunnel lining, track laying and installation of railway safety systems.
The 45-km broad-gauge railway line passes through Darjeeling and Kalimpong districts of West Bengal and Pakyong district of Sikkim. Around 86 per cent of its route runs through tunnels, reflecting the challenging mountainous terrain.
The project also involves the construction of 23 bridges and will have stations at Sivok, Riyang, Melli and Rangpo, besides an underground halt at Teesta Bazaar. At Sivok, the new line will connect with the existing New Jalpaiguri-Alipurduar railway route.
Once operational, the railway line will provide Sikkim with direct rail connectivity for the first time, offering residents and tourists an alternative to National Highway 10. It is also expected to improve the transportation of essential goods, expand market access for local businesses and support tourism in the state.